Under Virginia law, what is the outside deadline for the Commission to issue a resident license that requires an examination, measured from the date the applicant satisfies the prelicensing examination requirement?

Select an option to reveal the answer and the full 3-part explanation — free, no signup.

Answer & full 3-part explanation (select an option above, or peek)

Why B is correct

Va. Code § 38.2-1819 provides that no resident license requiring an examination shall be issued later than 183 calendar days from the date the applicant satisfies the prelicensing examination requirements. An applicant who fails to complete licensing within that window must satisfy all prelicensing requirements, including the examination, again before applying. Keeping 183 days distinct from the 180-day temporary-license period is a classic Virginia trap, and the Virginia Bureau of Insurance administers both clocks.

Why the other options are wrong

  • A) 30 days is a reporting and waiver-decision deadline elsewhere in Virginia insurance law, not the license-issuance window.
  • C) 180 days is the duration of a temporary license, not the issuance deadline, and the clock runs from satisfying the examination requirement, not from the application date.
  • D) 90 days is not the statutory issuance deadline for an examination-required license.

Memory hook

Pass the exam, then move fast — 183 days or start over.

Keep studying

Related Practice Questions

Your study shortcut

Install PassSprint

Add PassSprint to your Home Screen and open it like an app whenever you're ready to practice.

  1. Open this website in Chrome.
  2. Tap the three-dot menu (⋮) at the top right.
  3. Choose Install app or Add to Home screen → Install, then confirm.

Once added, tap the PassSprint icon on your Home Screen to get started.

Can't find the install option?

If you opened this link inside another app, copy it and open it in Chrome. Menu names can vary by browser.